BUREAU OF INDIAN STANDARDS
Programme of Work
CED43 : Soil And Foundation Engineering
- Scope : Formulation of indian standards in the field of soil and soil engineering covering: i) Sub-surface exploration (other than river valley projects); ii) Soil sampling and testing including stabilzed soils; iii) Soil classification for engineering purposes; iv) Load bearing capacities of soils; and v) Ground improvement techniques. Standardization in the field of foundation engineering in particular design requirements and construction practices for various types of foundations and special load tests on foundations
-
Liaison :ISO/TC 182 - Geotechnics - Observer (O)
IS 10042 : 1981 Reviewed In : 2021 |
Code of practice for site investigations for foundation in gravel - Boulder deposit
|
December, 2021
|
-
|
Indigenous
|
|
IS 10074 : 1982 Reviewed In : 2020 |
Specification for compaction mould assembly for light and heavy compaction test for soils
|
May, 2020
|
-
|
Indigenous
|
|
IS 10077 : 1982 Reviewed In : 2020 |
Specification for equipment for determination of shrinkage factors
|
May, 2020
|
-
|
Indigenous
|
|
IS 10108 : 1982 Reviewed In : 2020 |
Code of practice for sampling of soils by thin wall sampler with stationary piston
|
May, 2020
|
-
|
Indigenous
|
|
IS 10270 : 1982 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Guidelines for design and construction of prestressed rock anchors
|
November, 2023
|
2
|
Indigenous
|
|
IS 10379 : 1982 Reviewed In : 2020 |
Code of practice for field control of moisture and compaction of soils for embankment and subgrade
|
May, 2020
|
-
|
||
IS 10442 : 1983 Reviewed In : 2020 |
Specification for earth augers (Spiral Type)
|
May, 2020
|
-
|
Indigenous
|
|
IS 10589 : 1983 Reviewed In : 2020 |
Specification for equipment for subsurface sounding of soils
|
May, 2020
|
1
|
Indigenous
|
|
IS 1080 : 1985 Reviewed In : 2021 |
Code of practice for design and construction of shallow foundations in soils (Other Than Raft, Ring And Shell) (Second Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 10837 : 1984 Reviewed In : 2020 |
Moulds And Accessories For Determination Of Density Index (relative Density) Of Cohesionless Soils
|
May, 2020
|
-
|
||
IS 11089 : 1984 Reviewed In : 2021 |
Code of practice for design and construction of ring foundation
|
December, 2021
|
1
|
Indigenous
|
|
IS 11196 : 1985 Reviewed In : 2020 |
Specification for equipment for determination of liquid limit of soils cone penetration met - Hod
|
May, 2020
|
1
|
Indigenous
|
|
IS 11209 : 1985 Reviewed In : 2020 |
Specification for mould assembly for determination of permeability of soils
|
May, 2020
|
-
|
Indigenous
|
|
IS 11229 : 1985 Reviewed In : 2020 |
Specification for shear box for testing of soils
|
May, 2020
|
-
|
Indigenous
|
|
IS 11233 : 1985 Reviewed In : 2021 |
Code of practice for design and construction of radar antenna, microwave and TV tower foundations
|
December, 2021
|
-
|
||
IS 11550 : 1985 Reviewed In : 2021 |
Code of practice for field instrumentation of swelling pressure in expansive soils
|
December, 2021
|
-
|
Indigenous
|
|
IS 11593 : 1986 Reviewed In : 2020 |
Shear Box (large) For Testing Of Soils
|
May, 2020
|
-
|
||
IS 11594 : 1985 Reviewed In : 2020 |
Specification for mild steel thin walled samplnig tubes and sampler heads
|
May, 2020
|
-
|
Indigenous
|
|
IS 11629 : 1986 Reviewed In : 2021 |
Code of practice for installation and operation of single point hydraulic over - Flow setting gauge
|
December, 2021
|
-
|
Indigenous
|
|
IS 12023 : 1987 Reviewed In : 2020 |
Code of Practice for Field Monitoring of Movement of Structures Using Tape Extensometer
|
May, 2020
|
-
|
||
IS 12070 : 1987 Reviewed In : 2020 |
Code of practice for design and construction of shallow foundations on rocks
|
May, 2020
|
2
|
Indigenous
|
|
IS 12175 : 1987 Reviewed In : 2021 |
Specification for rapid moisture meter for rapid determination of water content for soil
|
December, 2021
|
-
|
Indigenous
|
|
IS 12208 : 1987 Reviewed In : 2020 |
Method for measurement of earth pressure by hydraulic pressure cell
|
May, 2020
|
-
|
Indigenous
|
|
IS 12287 : 1988 Reviewed In : 2020 |
Specification for consolidometer for determination of consolidation properties
|
May, 2020
|
-
|
Indigenous
|
|
IS 12979 : 1990 Reviewed In : 2020 |
Mould for determination of linear shrinkage - Specification
|
May, 2020
|
-
|
Indigenous
|
|
IS 13094 : 2021 |
Selection of ground improvement techniques for foundation in weak soils - Guidelines (first revision)
|
-
|
Indigenous
|
||
IS 13301 : 1992 Reviewed In : 2021 |
Vibration isolation for machine foundations - Guidelines
|
December, 2021
|
-
|
||
IS 13468 : 1992 Reviewed In : 2021 |
Apparatus for Determination of Dry Density of Soil by Core Cutter Method-
|
December, 2021
|
-
|
||
IS 14593 : 1998 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Design and construction of bored cast-in-situ piles founded on rocks - Guidelines
|
November, 2023
|
1
|
||
IS 14893 : 2021 |
Low strain non-destructive integrity testing of piles - Guidelines (first revision)
|
-
|
Indigenous
|
||
IS 1498 : 1970 Reviewed In : 2021 |
Classification and identification of soils for general engineering purposes (First Revision)
|
December, 2021
|
2
|
Not Equivalent
|
|
IS 15284 (Part 1) : 2003 Reviewed In : 2023 |
Design and construction for ground improvement - Guidelines: Part 1 stone columns
|
June, 2023
|
-
|
Indigenous
|
|
IS 15284 (Part 2) : 2004 Reviewed In : 2020 |
Design and construction for ground improvement - Guidelines: Part 2 preconsolidation using vertical drains
|
May, 2020
|
-
|
Indigenous
|
|
IS 1888 : 1982 Reviewed In : 2021 |
Method of load test on soils (Second Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 1892 : 2021 |
Subsurface investigation for foundations — Code of practice (second revision)
|
-
|
Indigenous
|
||
IS 1904 : 2021 |
General requirements for design and construction of foundations in soils — Code of practice (fourth revision)
|
-
|
Indigenous
|
||
IS 2131 : 1981 Reviewed In : 2021 |
Method for Standard Penetration Test for Soils (First Revision)
|
December, 2021
|
-
|
||
IS 2132 : 1986 Reviewed In : 2021 |
Code of Practice for Thin-Walled Tube Sampling of Soils (Second Revision)
|
December, 2021
|
-
|
||
IS 2720 (Part 1) : 1983 Reviewed In : 2020 |
Methods of test for soils: Part 1 preparation of dry soil samples for various tests (Second Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2720 (Part 2) : 1973 Reviewed In : 2020 |
Methods of test for soils: Part 2 determination of water content (Second Revision)
|
May, 2020
|
1
|
Not Equivalent
|
|
IS 2720 (Part 3/Sec 1) : 1980 Reviewed In : 2021 |
Methods of Test for Soils: Part 3 Determination of Specific Gravity: Section 1 Fine Grained Soils (First Revision)
|
December, 2021
|
-
|
||
IS 2720 (Part 3/Sec 2) : 1980 Reviewed In : 2021 |
Methods of Test for Soils: Part 3 Determination of Specific Gravity: Section 2 Fine, Medium and Coarse Grained Soils (First Revision)
|
December, 2021
|
-
|
||
IS 2720 (Part 4) : 1985 Reviewed In : 2020 |
Methods of test for soils: Part 4 grain size analysis (Second Revision)
|
May, 2020
|
-
|
Not Equivalent
|
|
IS 2720 (Part 5) : 1985 Reviewed In : 2020 |
Methods of test for soils: Part 5 determination of liquid and plastic limit (Second Revision)
|
May, 2020
|
-
|
Not Equivalent
|
|
IS 2720 (Part 6) : 1972 Reviewed In : 2021 |
Methods of test for soils: Part 6 determination of shrinkage factors (First Revision)
|
December, 2021
|
1
|
Indigenous
|
|
IS 2720 (Part 7) : 1980 Reviewed In : 2021 |
Methods of test for soils: Part 7 determination of water content - Dry density relation using light compaction (Second Revision)
|
December, 2021
|
2
|
Indigenous
|
|
IS 2720 (Part 8) : 1983 Reviewed In : 2020 |
Methods of test for soils: Part 8 determination of water content - Dry density relation using heavy compaction (Second Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2720 (Part 9) : 1992 Reviewed In : 2021 |
Methods of test for soils: Part 9 determination of dry density - Moisture content relation by constant mass of soil method (First Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 10) : 1991 Reviewed In : 2020 |
Methods of test for soils: Part 10 determination of unconfined compressive strength (Second Revision)
|
May, 2020
|
-
|
Not Equivalent
|
|
IS 2720 (Part 11) : 1993 Reviewed In : 2021 |
Methods of test for soils: Part 11 determination of the shear strength parameters of a specimen tested in unconsolidated undrained triaxial compression without the measurement of pore water pressure (First Revision)
|
December, 2021
|
-
|
Not Equivalent
|
|
IS 2720 (Part 12) : 1981 Reviewed In : 2021 |
Methods of test for soils: Part 12 determination of shear strength parameters of soil from consolidated undrained triaxial compression test with measurement of pore water pressure (First Revision)
|
December, 2021
|
-
|
Not Equivalent
|
|
IS 2720 (Part 13) : 1986 Reviewed In : 2021 |
Methods of test for soils: Part 13 Direct shear test
|
December, 2021
|
1
|
||
IS 2720 (Part 14) : 1983 Reviewed In : 2020 |
Methods of test for soils: Part 14 determination of density index (Relative Density) of cohesionless soils (First Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2720 (Part 15) : 1965 Reviewed In : 2021 |
Methods of test for soils: Part 15 determination of consolidation properties (First Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 16) : 1987 Reviewed In : 2021 |
Methods of test for soils: Part 16 laboratory determination of cbr (Second Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 17) : 1986 Reviewed In : 2021 |
Methods of test for soils: Part 17 laboratory determination of permeability (First Revision)
|
December, 2021
|
-
|
Not Equivalent
|
|
IS 2720 (Part 18) : 1992 Reviewed In : 2021 |
Methods of test for soils: Part 18 determination of field moisture equivalent (First Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 19) : 1992 Reviewed In : 2021 |
Methods of test for soils: Part 19 determination of centrifuge moisture equivalent (First Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 20) : 1992 Reviewed In : 2021 |
Methods of test for soils: Part 20 determination of linear shrinkage (First Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 21) : 1977 Reviewed In : 2020 |
Methods of test for soils: Part 21 determination of total soluble solids (First Revision)
|
May, 2020
|
1
|
Indigenous
|
|
IS 2720 (Part 22) : 1972 Reviewed In : 2020 |
Methods of test for soils: Part 22 determination of organic matter (First Revision)
|
May, 2020
|
1
|
Indigenous
|
|
IS 2720 (Part 23) : 1976 Reviewed In : 2020 |
Methods of test for soils: Part 23 Determination of calcium carbonate
|
May, 2020
|
-
|
||
IS 2720 (Part 24) : 1976 Reviewed In : 2020 |
Methods of test for soils: Part 24 determination of cation exchange capacity (First Revision)
|
May, 2020
|
1
|
Not Equivalent
|
|
IS 2720 (Part 25) : 1982 Reviewed In : 2020 |
Methods of test for soils: Part 25 determination silica sesquioxide ratio (First Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2720 (Part 26) : 1987 Reviewed In : 2021 |
Method of test for soils: Part 26 determination of pH value (Second Revision)
|
December, 2021
|
-
|
Not Equivalent
|
|
IS 2720 (Part 27) : 1977 Reviewed In : 2020 |
Methods of test for soils: Part 27 determination of total soluble sulphates (First Revision)
|
May, 2020
|
-
|
Not Equivalent
|
|
IS 2720 (Part 28) : 1974 Reviewed In : 2020 |
Methods of test for soils: Part 28 determination of dry density of soils, in - Place, by the sand replacement method (First Revision)
|
May, 2020
|
1
|
Not Equivalent
|
|
IS 2720 (Part 29) : 1975 Reviewed In : 2020 |
Methods of test for soils: Part 29 determination of dry density of soils in - Place by the core - Cutter method (First Revision)
|
May, 2020
|
-
|
Not Equivalent
|
|
IS 2720 (Part 30) : 1980 Reviewed In : 2021 |
Methods of test for soils: Part 30 Laboratory vane shear test
|
December, 2021
|
1
|
||
IS 2720 (Part 31) : 1990 Reviewed In : 2020 |
Methods of Test for soils: Part 31 Field Determination of California Bearing Ratio (First Revision)
|
May, 2020
|
-
|
||
IS 2720 (Part 33) : 1971 Reviewed In : 2020 |
Methods of test for soils: Part 33 Determination of the density in place by the ring and water replacement method
|
May, 2020
|
1
|
||
IS 2720 (Part 34) : 1972 Reviewed In : 2020 |
Methods of test for soils: Part 34 Determination of density of soil in-place by rubber-balloon method
|
May, 2020
|
1
|
||
IS 2720 (Part 35) : 1974 Reviewed In : 2020 |
Methods of test for soils: Part 35 Measurement of negative pore water pressure
|
May, 2020
|
-
|
||
IS 2720 (Part 36) : 1987 Reviewed In : 2021 |
Methods of Test for Soils: Part 36 Laboratory Determination of Permeability of Granular Soils (Constant Head) (First Revision)
|
December, 2021
|
-
|
||
IS 2720 (Part 37) : 1976 Reviewed In : 2021 |
Methods of test for soils: Part 37 Determination of sand equivalent values of soils and fine aggregates
|
December, 2021
|
-
|
||
IS 2720 (Part 38) : 1976 Reviewed In : 2021 |
Methods of test for soils: Part 38 Compaction control test (Hilf method)
|
December, 2021
|
-
|
||
IS 2720 (Part 39/Sec 1) : 1977 Reviewed In : 2021 |
Methods of test for soils: Part 39 Direct shear test for soils containing gravel, Section 1 Laboratory test
|
December, 2021
|
2
|
||
IS 2720 (Part 39/Sec 2) : 1979 Reviewed In : 2021 |
Methods of test for soils: Part 39 Direct shear test for soils containing gravel, Section 2 In-situ shear test
|
December, 2021
|
-
|
||
IS 2720 (Part 40) : 1977 Reviewed In : 2021 |
Methods of test for soils: Part 40 determination of free swell index of soils
|
December, 2021
|
-
|
Indigenous
|
|
IS 2720 (Part 41) : 1977 Reviewed In : 2021 |
Methods of test for soils: Part 41 measurement of swelling pressure of soils
|
December, 2021
|
-
|
Indigenous
|
|
IS 2809 : 1972 Reviewed In : 2020 |
Glossary of terms and symbols relating to soil engineering (First Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2810 : 1979 Reviewed In : 2021 |
Glossary of terms relating to soil dynamics (First Revision)
|
December, 2021
|
-
|
Indigenous
|
|
IS 2911 (Part 1/Sec 1) : 2010 Reviewed In : 2020 |
Design and construction of pile foundations - Code of practice: Part 1 concrete piles: Sec 1 driven cast in-situ concrete piles (Second Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2911 (Part 1/Sec 2) : 2010 Reviewed In : 2020 |
Design and construction of pile foundations - Code of practice: Part 1 concrete piles: Sec 2 bored cast in-situ concrete piles (Second Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2911 (Part 1/Sec 3) : 2010 Reviewed In : 2020 |
Design and Construction of Pile Foundations — Code Of Practice Part 1 Concrete Piles: Section 3 Driven Precast Concrete Piles (Second Revision)
|
May, 2020
|
-
|
||
IS 2911 (Part 1/Sec 4) : 2010 Reviewed In : 2020 |
Design and construction of pile foundations - Code of practice: Part 1 concrete piles: Sec 4 precast concrete piles in prebored holes (First Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 2911 (Part 2) : 2021 |
Design and construction of pile foundation - Code of practice: Part 2 Timber piles (second revision)
|
-
|
Indigenous
|
||
IS 2911 (Part 3) : 2021 |
Design and construction of pile foundations - Code of practice: Part 3 Under-reamed piles (second revision)
|
-
|
Indigenous
|
||
IS 2911 (Part 4) : 2013 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Design and construction of pile foundations - Code of practice: Part 4 load test on piles (Second Revision)
|
November, 2023
|
-
|
Not Equivalent
|
|
IS 2950 (Part 1) : 1981 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Code of practice for design and construction of raft foundations: Part 1 design (Second Revision)
|
November, 2023
|
1
|
Indigenous
|
|
IS 2974 (Part 1) : 1982 Reviewed In : 2023 |
Code of practice for design and construction of machine foundations: Part 1 foundation for reciprocating type machines (Second Revision)
|
November, 2023
|
1
|
Indigenous
|
|
IS 2974 (Part 2) : 1980 Reviewed In : 2023 |
Code of pracrrIce for design and construction of machine foundations: Part 2 foundations for impact type machines (Hammer Foundations) (First Revision)
|
November, 2023
|
1
|
Indigenous
|
|
IS 2974 (Part 3) : 1992 Reviewed In : 2020 |
Code of practice for design and construction of machine foundations: Part 3 Foundations for rotary type machines (Medium and high frequency)
|
May, 2020
|
-
|
||
IS 2974 (Part 4) : 1979 Reviewed In : 2020 |
Code of practice for design and construction of machine foundations: Part 4 foundations for rotary type machines of low frequency
|
May, 2020
|
1
|
Indigenous
|
|
IS 2974 (Part 5) : 1987 Reviewed In : 2023 |
Code of practice for design and construction of machine foundations: Part 5 foundations for impact machines other than hammer (Forging and stamping press, pig breaker, drop crusher and jolter) (First Revision)
|
November, 2023
|
-
|
Indigenous
|
|
SP 36-1 : 1987 |
Compendium of Indian Standards on Soil Engineering: Part-1 LaboratoryTesting of Soils for civil Engineering Purposes
|
-
|
|||
SP 36-2 : 1988 |
Compendium of Indian Standards on Soil Engineering: Part-2 Field Testing of Soils For Civil Engineering Purposes
|
-
|
|||
IS 4091 : 1979 Reviewed In : 2020 |
Code of practice for design and construction of foundations for transmission line towers and poles (First Revision)
|
May, 2020
|
-
|
Indigenous
|
|
IS 4332 (Part 1) : 1967 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 1 Method of sampling and preparation of stabilized soils for testing
|
May, 2020
|
1
|
||
IS 4332 (Part 2) : 1967 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 2 Determination of moisture content of stabilized soil mixtures
|
May, 2020
|
1
|
Indigenous
|
|
IS 4332 (Part 3) : 1967 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 3 Test for determination of moisture content-dry density relation for stablized soil mixtures
|
May, 2020
|
1
|
||
IS 4332 (Part 4) : 1968 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 4 Wetting and drying, and freezing and thawing tests for compacted soil-cement mixtures
|
May, 2020
|
1
|
||
IS 4332 (Part 5) : 1970 Reviewed In : 2020 |
Methods of test for stabilizd soils: Part 5 Determination of unconfined compressive strength of stablized soils
|
May, 2020
|
-
|
||
IS 4332 (Part 6) : 1972 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 6 Flexural strength of soil-cement using simple beam with third-point loading
|
May, 2020
|
1
|
||
IS 4332 (Part 7) : 1973 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 7 Determination of cement content of cement stabilized soils
|
May, 2020
|
1
|
||
IS 4332 (Part 8) : 1969 Reviewed In : 2020 |
Methods of test for stablized soils: Part 8 Determination of lime content of lime stablized soils
|
May, 2020
|
1
|
||
IS 4332 (Part 9) : 1970 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 9 Determination of the bituminous stabilizer content of bitumen and tar stabilized soils
|
May, 2020
|
1
|
||
IS 4332 (Part 10) : 1969 Reviewed In : 2020 |
Methods of test for stabilized soils: Part 10 Test for soil-bituminous mixtures
|
May, 2020
|
1
|
||
IS 4434 : 1978 Reviewed In : 2021 |
Code Of Practice For In-situ Vane Shear Test For Soils
|
December, 2021
|
-
|
||
IS 4968 (Part 1) : 1976 Reviewed In : 2021 |
Method for subsurface sounding for soils: Part 1 dynamic method using 50 mm cone without bentonite slurry (First Revision)
|
December, 2021
|
2
|
Not Equivalent
|
|
IS 4968 (Part 2) : 1976 Reviewed In : 2021 |
Method for subsurface sounding for soils: Part 2 dynamic method using cone and bentonite slurry (First Revision)
|
December, 2021
|
2
|
Not Equivalent
|
|
IS 4968 (Part 3) : 1976 Reviewed In : 2021 |
Method for subsurface sounding for soils: Part 3 Static cone penetration test
|
December, 2021
|
-
|
||
IS 5249 : 1992 Reviewed In : 2020 |
Determination of dynamic properties of soil - Method of test (Second Revision)
|
May, 2020
|
1
|
Indigenous
|
|
IS 6403 : 1981 Reviewed In : 2021 |
Code of practice for determination of bearing capacity of shallow foundations
|
December, 2021
|
2
|
||
IS 8009 (Part 1) : 1976 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Code of practice for calculation of settlements of foundations: Part 1 shallow foundations subjected to symmetrical static vertical loads
|
November, 2023
|
3
|
Indigenous
|
|
IS 8009 (Part 2) : 1980 Reviewed In : 2020 |
Code of practice for calculation of settlement of foundations: Part 2 deep foundations subjected to symmetrical static vertical loading z
|
May, 2020
|
1
|
Indigenous
|
|
IS 8763 : 1978 Reviewed In : 2021 |
Guide for undistrubed sampling of sands
|
December, 2021
|
-
|
||
IS 9198 : 1979 Reviewed In : 2021 |
Specification for compaction rammer for soil testing
|
December, 2021
|
1
|
Indigenous
|
|
IS 9214 : 1979 Reviewed In : 2021 |
Method of determination of modulus of subgrade reaction (K - Value) of soils in field
|
December, 2021
|
1
|
Indigenous
|
|
IS 9259 : 1979 Reviewed In : 2021 |
Specification for liquid limit apparatus for soils
|
December, 2021
|
1
|
Indigenous
|
|
IS 9456 : 1980 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Code of practice for design and construction of conical and hyperbolic paraboloidal types of shell foundations
|
November, 2023
|
1
|
Indigenous
|
|
IS 9556 : 1980 Reviewed In : 2023 Decision taken to Reaffirm and Archive |
Code of practice for design and construction of diaphragm walls
|
November, 2023
|
1
|
Indigenous
|
|
IS 9640 : 1980 Reviewed In : 2021 |
Specification for split spoon sampler
|
December, 2021
|
2
|
Indigenous
|
|
IS 9669 : 1980 Reviewed In : 2021 |
Specification for cbr moulds and its accessories
|
December, 2021
|
2
|
Indigenous
|
|
IS 9716 : 1981 Reviewed In : 2021 |
Guide for lateral dynamic load test on piles
|
November, 2021
|
-
|
Indigenous
|
|
IS 9759 : 1981 Reviewed In : 2021 |
Guidelines for dewatering during construction
|
November, 2021
|
1
|
Indigenous
|
No Records Found |
No Records Found |
No Records Found |
CED 43 (21115)
Revision of: IS 2131:1981 |
Standard Penetration Test of Soil Method of Test |
|
CED 43 (24470)
Revision of: IS 15284:2003 |
Design and Construction for Ground Improvement Code of Practice Part 1 Stone Columns |
|
CED 43 (24471)
Revision of: IS 15284:2004 |
Design and Construction for Ground Improvement - Code of Practice Part 2 Preconsolidation Using Vertical Drains |
|
CED 43 (26407)
Revision of: IS 2720:1983 |
Soils Methods of Test Part 1 Preparation of Dry Soil Samples for Various Tests |
|
CED 43 (26408)
Revision of: IS 2720:1973 |
Soils Methods of Test Part 2 Determination of Water Content |
|
CED 43 (26411)
Revision of: IS 4091:1979 |
Design and Construction of Foundations for Transmission Line Towers and Poles Code of Practice Second revision of IS 4091 |
|
CED 43 (26416)
Revision of: IS 11233:1985 |
Design and Construction of Foundations for Radar and Satellite Tracking Antennas and Microwave Mobile and Television Towers Code of Practice First Revision |
|
CED 43 (26424)
Revision of: IS 2974:1982 |
Design and Construction of Machine Foundations Code of Practice Part 1 General Provisions Third Revision |
|
CED 43 (26425)
Revision of: IS 2974:1980 |
Design and Construction of Machine Foundations Code of Practice Part 2 Block Foundations First Revision |
|
CED 43 (26426)
Revision of: IS 2974:1992 |
Design and Construction of Machine Foundations Code of Practice Part 3 Frame Foundations First Revision |
|
CED 43 (26427)
Revision of: IS 2974:1979 |
Design and Construction of Machine Foundations Code of Practice Part 4 Foundations for Hammers and Presses Second Revision |
No Records Found |
CED 43 (20668)
Revision of: IS 10077:1982 |
Equipment for Determination of Shrinkage Factors - Specification First Revision | |
CED 43 (20669)
Revision of: IS 11196:1985 |
Equipment for Determination of Liquid Limit of Soils by Cone Penetration Method - Specification First Revision | |
CED 43 (20670)
Revision of: IS 9669:1980 |
CBR Mould and Its Accessories - Specification First Revision | |
CED 43 (20693)
Revision of: IS 10442:1983 |
Earth Augers Spiral Type - Specification First Revision | |
CED 43 (20812)
Revision of: IS 9259:1979 |
Casagrande Apparatus for Determination of Liquid Limit of Soils by Impact Method - Specification First Revision | |
CED 43 (21048)
Revision of: IS 11209:1985 |
Mould Assembly for Determination of Permeability of Soils - Specification First Revision | |
CED 43 (21049)
Revision of: IS 11229:1985 |
Shear Box for Testing of Soils - Specification First Revision | |
CED 43 (21050)
Revision of: IS 12175:1987 |
Rapid Moisture Meter for Rapid Determination of Water Content of Soil Specification First Revision | |
CED 43 (21137)
Revision of: IS 9198:1979 |
Compaction Rammers for Soil Testing Specification First Revision | |
CED 43 (21138)
Revision of: IS 11594:1985 |
Mild Steel Thin Walled Sampling Tubes and Sampler Heads Specification First Revision | |
CED 43 (21162)
Revision of: IS 12979:1990 |
Mould for determination of linear shrinkage of soil Specification First Revision | |
CED 43 (21226)
Revision of: IS 13468:1992 |
Apparatus for Determination of Dry Density of Soil by Core Cutter Method Specification First Revision | |
CED 43 (21227)
Revision of: IS 10074:1982 |
Compaction Mould Assembly for Light and Heavy Compaction Test of Soil Specification First Revision | |
CED 43 (21232)
Revision of: IS 11593:1986 |
Shear Box Large for Testing of Soils Specification First Revision | |
CED 43 (21297)
Revision of: IS 10837:1984 |
Moulds and accessories for determination of density index relative density of cohesionless soils Specification First Revision | |
CED 43 (21298)
Revision of: IS 12287:1988 |
Consolidometer for determination of consolidation properties of soil Specification First Revision | |
CED 43 (21409)
|
Design and construction of combined piled raft foundations - Code of practice | |
CED 43 (22265)
Revision of: IS 9640:1980 |
Split spoon sampler for standard penetration test of soil Specification First Revision |
|
IS 3955 : 1967 Reviewed In : 2005 |
Code of practice for design and construction of well foundations |
IS 10074 : 1982 Reviewed In : 2020 |
Specification for compaction mould assembly for light and heavy compaction test for soils |
|
IS 10077 : 1982 Reviewed In : 2020 |
Specification for equipment for determination of shrinkage factors |
|
IS 10442 : 1983 Reviewed In : 2020 |
Specification for earth augers Spiral Type |
|
IS 10589 : 1983 Reviewed In : 2020 |
Specification for equipment for subsurface sounding of soils |
|
IS 10837 : 1984 Reviewed In : 2020 |
Moulds And Accessories For Determination Of Density Index relative Density Of Cohesionless Soils |
|
IS 11196 : 1985 Reviewed In : 2020 |
Specification for equipment for determination of liquid limit of soils cone penetration met - Hod |
|
IS 11209 : 1985 Reviewed In : 2020 |
Specification for mould assembly for determination of permeability of soils |
|
IS 11229 : 1985 Reviewed In : 2020 |
Specification for shear box for testing of soils |
|
IS 11593 : 1986 Reviewed In : 2020 |
Shear Box large For Testing Of Soils |
|
IS 11594 : 1985 Reviewed In : 2020 |
Specification for mild steel thin walled samplnig tubes and sampler heads |
|
IS 12175 : 1987 Reviewed In : 2021 |
Specification for rapid moisture meter for rapid determination of water content for soil |
|
IS 12287 : 1988 Reviewed In : 2020 |
Specification for consolidometer for determination of consolidation properties |
|
IS 12979 : 1990 Reviewed In : 2020 |
Mould for determination of linear shrinkage - Specification |
|
IS 13468 : 1992 Reviewed In : 2021 |
Apparatus for Determination of Dry Density of Soil by Core Cutter Method- |
|
IS 9198 : 1979 Reviewed In : 2021 |
Specification for compaction rammer for soil testing |
|
IS 9259 : 1979 Reviewed In : 2021 |
Specification for liquid limit apparatus for soils |
|
IS 9640 : 1980 Reviewed In : 2021 |
Specification for split spoon sampler |
|
IS 9669 : 1980 Reviewed In : 2021 |
Specification for cbr moulds and its accessories |