Document Details |
|||||
Name of Department/Committee : | ETD 36 | ||||
---|---|---|---|---|---|
Document Number : | ETD 36 ( 27201) | ||||
Document Title [English] : | Live working - Minimum approach distances - Part 1: AC systems in the voltage range 725 kV to 800 kV - A method of calculation (Second Revision) | ||||
Document Title [Hindi] : | चालू बिजली की लाईन पर कार्य करना- भाग 1: 72.5kV से 800 kV तक की वोल्टेज रेंज में दिष्ट धारा प्रणाली हेतु न्यूनतम उपगमन ( दूसरा पुनरीक्षण ) | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 2 | ||||
ICS Code : | 13.260; 29.240.20; 29.260.99 | ||||
Date of Project Approval : | 07-08-2024 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Electrical installations and general electricals |
Sub Sub Group : | Tools and Equipments for live working |
Aspects : | System Standard |
Risk : | Medium |
Certification : | Not Certifiable |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Identical under dual numbering |
Identical/Equivalent Standards : | IEC 61472: 2013 |
Organization Type: | IEC |
Sl.No. | Synosis Points | |
1 | This standards cover a method for calculating the minimum approach distances for live working, at maximum voltages between 72,5 kV and 800 kV. This standard addresses system overvoltages and the working air distances or tool insulation between parts and/or workers at different electric potentials. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 07-08-2024 | ------- | ||
2 | P-Draft | 03-01-2025 | Covering letter generated | ------- | |
3 | P-Draft | 03-01-2025 | Duration : 30 Days | ETD 36, | ------- |
4 | Skipped to W-Draft | 14-02-2025 | Stage-Changed | ------- | |
5 | WC Draft | 14-02-2025 | Duration : 30 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 18-02-2025 | WC approved by HOD |
ETDC ETD 36, | ------- |