Document Details
Name of Department/Committee : WRD 23
Document Number : WRD 23 ( 27479)
Document Title [English] : METHODS OF MEASUREMENT OF WORK IN RIVER VALLEY PROJECTS DAMS AND APPURTENANT STRUCTURES PART 12 TOPOGRAPHICAL SURVEYS
Document Title [Hindi] : नदी घाटी परियोजनाओं में कार्य मापन की पद्धति (बाँध और संबंध संरचनाएं) भाग 12 स्थलाकृतिक सर्वेक्षण
Document Type : Revision
Language : English
Priority : 3
ICS Code : 93.160
Date of Project Approval : 21-08-2024
Standards to be Revised :
Sl.No. Is No & Year
1 IS 9401 : Part 12: 1992
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 9401 : Part 12: 1992


Classification Details
Group : Civil Engineering Design and Construction
Sub Group : Hydraulic and other related structures
Sub Sub Group : Geological Maps, subsurface Exploratory Logs and Geological Explorations for river valley projects
Aspects : Code of Practice
Risk : Low
Certification : None
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Jal Shakti - Department of Water Resources, River Development and Ganga Rejuvenation
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 In measurement of works of river projects a large diversity of methods exist at present according to local practices. This lack of uniformity creates complications regarding measurements and payments. Keeping in view the large amount of financial outlay involved in river valley projects and also the fact that the authorities responsible for completing these projects, are of the state level or national level, it is felt that a suitable methodology is needed for adopting uniform practices towards the measurement of works so that the scope of complications and misinterpretation of items of work is reduced, as far as possible. This standard is intended to provide a uniform basis for measuring the work done in respect of topographical surveys for river valley projects.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 29-01-2025 29-06-2025 13-09-2025 28-01-2026 Mr. Vaibhav Yadav 29-01-2025
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 21-08-2024 -------
2 P-Draft Waived 29-01-2025 -------
3 WC Draft 29-01-2025 Duration : 60 Days
Submitted for HOD approval
-------
4 WC Draft 31-01-2025 WC rejected by HOD
Remarks: Resubmit with correction
-------
5 WC Draft 03-02-2025 Duration : 60 Days
Submitted for HOD approval
-------
6 WC Draft 03-02-2025 WC approved by HOD
WRDC   -------