Document Details |
|||||
Name of Department/Committee : | WRD 23 | ||||
---|---|---|---|---|---|
Document Number : | WRD 23 ( 27479) | ||||
Document Title [English] : | METHODS OF MEASUREMENT OF WORK IN RIVER VALLEY PROJECTS DAMS AND APPURTENANT STRUCTURES PART 12 TOPOGRAPHICAL SURVEYS | ||||
Document Title [Hindi] : | नदी घाटी परियोजनाओं में कार्य मापन की पद्धति (बाँध और संबंध संरचनाएं) भाग 12 स्थलाकृतिक सर्वेक्षण | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | 93.160 | ||||
Date of Project Approval : | 21-08-2024 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Civil Engineering Design and Construction |
Sub Group : | Hydraulic and other related structures |
Sub Sub Group : | Geological Maps, subsurface Exploratory Logs and Geological Explorations for river valley projects |
Aspects : | Code of Practice |
Risk : | Low |
Certification : | None |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | In measurement of works of river projects a large diversity of methods exist at present according to local practices. This lack of uniformity creates complications regarding measurements and payments. Keeping in view the large amount of financial outlay involved in river valley projects and also the fact that the authorities responsible for completing these projects, are of the state level or national level, it is felt that a suitable methodology is needed for adopting uniform practices towards the measurement of works so that the scope of complications and misinterpretation of items of work is reduced, as far as possible. This standard is intended to provide a uniform basis for measuring the work done in respect of topographical surveys for river valley projects. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 21-08-2024 | ------- | ||
2 | P-Draft Waived | 29-01-2025 | ------- | ||
3 | WC Draft | 29-01-2025 | Duration : 60 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 31-01-2025 | WC rejected by HOD Remarks: Resubmit with correction |
------- | |
5 | WC Draft | 03-02-2025 | Duration : 60 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 03-02-2025 | WC approved by HOD |
WRDC | ------- |