Name of Department/Committee : | ETD 07 | ||||
---|---|---|---|---|---|
Document Number : | ETD 07 ( 26317) | ||||
Document Title [English] : | Low-Voltage Switchgear and Controlgear Assemblies Part 4: Particular requirements for assemblies for construction sites ACS First Revision | ||||
Document Title [Hindi] : | Low-Voltage Switchgear and Controlgear Assemblies – Part 4: Particular requirements for assemblies for construction sites (ACS) (First Revision) | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | ICS 29.130.20 | ||||
Date of Project Approval : | 06-08-2024 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Switchgear, Metering and Accessories |
Sub Sub Group : | Circuit breakers, switches and disconnectors |
Aspects : | Product Specification |
Risk : | Low |
Certification : | Voluntary Certification |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Identical under single numbering |
Identical/Equivalent Standards : | IEC 61439-4: 2024 |
Organization Type: | IEC |
Sl.No. | Synosis Points | |
1 | This part of 61439 defines the specific requirements of ACS as follows: – ASSEMBLIES for which the rated voltage does not exceed 1 000 V in case of a.c. or 1 500 V in case of d.c.; – ASSEMBLIES where the nominal primary voltage and the nominal secondary voltage of transformers incorporated in ACS are within the limits specified above; – ASSEMBLIES intended for use on construction sites, both indoors and outdoors, i.e. temporary places of work to which the public do not generally have access and where building construction, installation, repairs, alteration or demolition of property (buildings) or civil engineering (public works) or excavation or any other similar operations are carried out; – transportable (semi-fixed) or mobile ASSEMBLIES with enclosure. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 06-08-2024 | ------- | ||
2 | P-Draft | 07-08-2024 | Covering letter generated | ------- | |
3 | P-Draft | 07-08-2024 | Duration : 30 Days | ETD 7, | ------- |
4 | Skipped to W-Draft | 28-11-2024 | Stage-Changed | ------- | |
5 | WC Draft | 28-11-2024 | Duration : 60 Days Submitted for HOD approval Remarks : Since no comments were received during the P draft stage the Chairman of the ETD 07 Sectional Committee approved the documents for wide circulation for 60 days via email on 26-Nov-2024 |
------- | |
6 | WC Draft | 29-11-2024 | WC approved by HOD |
ETDC | ------- |