Document Title [English] : | Criteria for the design of reinforced concrete arches | ||||
Document Title [Hindi] : | प्रबलित कंक्रीट मेहराब के डिज़ाइन के लिए मानदंड | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | 91.080.40 | ||||
Date of Project Approval : | 10-10-2024 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Civil Engineering Design and Construction |
Sub Group : | Concrete structures |
Sub Sub Group : | Special Structures |
Aspects : | Code of Practice |
Risk : | Medium |
Certification : | None |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | This standard lays down recommendations for the classification, dimensional proportioning, analysis and design of reinforced concrete arches. The criteria for design is intended to apply only to arches which are primarily loaded (with dead and Impose loads) in their own plane and where curve lies in one plane. | |
2 | a) As IS 456 is revised considering state of the art of technology, provisions of this code are adopted wherever applicable. Wherever clarification is needed, IS 456 ‘Plain and reinforced concrete - Code of practice (fourth revision)’, may be referred to; b) Considering the developments in the reinforcing steel manufacturing industry high strength steels are adopted for use; c) Importance of durability and health of structures is identified as a primary factor for designing structure to last longer, provisions of IS 456 are referred, as applicable; d) Clauses on spandrel walls and drainage of spandrel fill has been included; e) Clauses on reinforcement has been updated; f) Clause on expansion joint has been included; g) Clauses on waterproofing has been included; and h) List of Indian Standard cross referred in this standard has been updated. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 10-10-2024 | ------- | ||
2 | P-Draft | 11-11-2024 | Covering letter generated | ------- | |
3 | P-Draft | 11-11-2024 | Duration : 21 Days | CED 38, CED 38, CED 38 : P4, | ------- |
4 | Skipped to W-Draft | 27-03-2025 | Stage-Changed | ------- | |
5 | WC Draft | 27-03-2025 | Duration : 33 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 27-03-2025 | WC approved by HOD |