Name of Department/Committee : | CED 30 | ||||
---|---|---|---|---|---|
Document Number : | CED 30 ( 26671) | ||||
Document Title [English] : | Heavy Duty Burnt Clay Building Bricks Specification | ||||
Document Title [Hindi] : | हेवी ड्यूटी जली हुई मिट्टी से बनी ईंटें – विशिष्टता | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | ICS No. 91.100.25 | ||||
Date of Project Approval : | 06-08-2024 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Building Materials including Paints |
Sub Group : | Clay products |
Sub Sub Group : | Bricks, blocks and other clay products |
Aspects : | Product Specification |
Risk : | Low |
Certification : | Voluntary Certification |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : |
|
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | The requirements of bricks to be free from flaws and nodules of free lime have been removed. | |
2 | It has been highlighted that bricks of 40 mm height are not recommended for structural use. | |
3 | The maximum individual variation of compressive strength from the mean value has been reduced to 15 percent. | |
4 | The concept of shape factor for 40mm high bricks have been introduced. | |
5 | The minimum bulk density of the bricks has been modified to 2 200 kg/cm3. | |
6 | The requirements for warpage have been revised. | |
7 | The provision to eliminate frogs in bricks of 40 mm made by extrusion process has been included. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 06-08-2024 | ------- | ||
2 | P-Draft | 01-10-2024 | Covering letter generated | ------- | |
3 | P-Draft | 01-10-2024 | Duration : 21 Days | CED 30, | ------- |
4 | Skipped to W-Draft | 09-01-2025 | Stage-Changed | ------- | |
5 | WC Draft | 09-01-2025 | Duration : 60 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 10-01-2025 | WC approved by HOD |
CEDC | ------- |