Document Details |
|||||||||||
Name of Department/Committee : | CED 43 | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Document Number : | CED 43 ( 26427) | ||||||||||
Document Title [English] : | Design and Construction of Machine Foundations Code of Practice: Part 4 Foundations for Hammers and Presses (Second Revision) | ||||||||||
Document Title [Hindi] : | भारतीय मानक मसौदा मशीन फाउंडेशन का डिजाइन और निर्माण - भाग 4 हथौड़ों और प्रेस के लिए नींव (दूसरा पुनरीक्षण ) | ||||||||||
Document Type : | Revision | ||||||||||
Language : | English | ||||||||||
Priority : | 3 | ||||||||||
ICS Code : | 93.020 | ||||||||||
Date of Project Approval : | 22-06-2024 | ||||||||||
Standards to be Revised : |
|
||||||||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Civil Engineering Design and Construction |
Sub Group : | Foundation, underground structures, soil and rock mechanics |
Sub Sub Group : | Soil Mechanics and Ground Improvement |
Aspects : | Code of Practice |
Risk : | Low |
Certification : | Not Certifiable |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | The various parts of the code have been restructured and the parts are now divided foundation-wise rather than machine-wise, except the part covering foundations for impact and impulsive load machines, that is, hammers and presses, where the foundation has to be necessarily machine-wise. | |
2 | This Part 4 deals with design and construction of hammer foundation subjected to stray and repeated impacts and where the ratio of mass of anvil to foundation is high. This Part also deals with design and construction of block type foundation of reinforced concrete for the installation of the machines like forging, sheet metal, stamping presses, scrap breakers or pig breakers and jolters. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 22-06-2024 | ------- | ||
2 | P-Draft Waived | 27-08-2024 | ------- | ||
3 | WC Draft | 27-08-2024 | Duration : 31 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 27-08-2024 | WC approved by HOD |
CEDC CED 46 : P5, | ------- |