Document Details
Name of Department/Committee : EED 01
Document Number : EED 01 ( 25248)
Document Title [English] : CARBON DIOXIDE CAPTURE PART 1: PERFORMANCE EVALUATON METHODS FOR POST-COMBUSTION CO2 CAPTURE INTEGRATED WITH A POWER PLANT
Document Title [Hindi] : कार्बन डाइऑक्साइड कैप्चर - भाग 1: एक विद्युत संयंत्र के साथ एकीकृत दहन के बाद CO2 कैप्चर के लिए प्रदर्शन मूल्यांकन विधियाँ
Document Type : New
Language : English
Priority : 3
ICS Code : 13.020.40
Date of Project Approval : 12-04-2024
Standards to be Superseded :


Classification Details
Group : Chemicals, Plastics and their Products including packaging and Environment
Sub Group : Environment management
Sub Sub Group : Environmental Management
Aspects : Code of Practice
Risk : None
Certification : None
Short Commom Man's Title : PERFORMANCE EVALUATON METHODS FOR POST-COMBUSTION CO2 CAPTURE INTEGRATED WITH A POWER PLANT
ITCHS Code :
Ministry :
  • Ministry of Environment, Forest and Climate Change
Sustainable development Goals :
  • CLIMATE ACTION
  • LIFE ON LAND
Degree of Equivalence : Identical under dual numbering
Identical/Equivalent Standards : ISO 27919 PART 1: 2018
Organization Type: ISO

Sl.No. Synosis Points
1 This standard specifies method for measuring, evaluating and reporting the performance of post-combustion CO2 capture (PCC) integrated with a power plant, and which separates CO2 from the power plant flue gas in preparation for subsequent transportation and geological storage, In particular, it provides a common methodology to calculate specific key performance indicators for the PCC plant, requiring the definition of the boundaries of a typical system and the measurements needed to determine the KPIs.
2 This standard coves thermal power plants burning carbonaceous fuels, such as coal, oil natural gas and biomass derived fuels, which are producing CO2¬ from boilers or gas turbines and are integrated with CO2 capture.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 12-04-2024 12-08-2024 12-09-2024 12-01-2025 Mr. MOHIT GARG 12-04-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 12-04-2024 -------
2 P-Draft Waived 15-04-2024 The Draft National Forward is approved for the wide circulation in the 31st meeting of CHD 34 -------
3 WC Draft 18-04-2024 Duration : 60 Days
Submitted for HOD approval
-------
4 WC Draft 19-04-2024 WC approved by HOD
EEDC  CHD 34, CHD 34 : 3, -------