Document Details |
|
Name of Department/Committee : | ETD 44 |
---|---|
Document Number : | ETD 44 ( 25966) |
Document Title [English] : | Safety of Machinery Electro-Sensitive Protective Equipment Part 5 Particular Requirements for Radar-Based Protective Devices |
Document Title [Hindi] : | मशीनों की सुरक्षा - विद्युत संवेदी संरक्षी उपकरण - भाग 5 रडार आधारित संरक्षी उपकरणों के लिए विशेष अपेक्षाएं |
Document Type : | New |
Language : | English |
Priority : | 2 |
ICS Code : | ICS 13.110; 29.260.99 |
Date of Project Approval : | 15-04-2021 |
Standards to be Superseded : |
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Electrical installations and general electricals |
Sub Sub Group : | National Electrical Code |
Aspects : | Safety Standard |
Risk : | Low |
Certification : | None |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Identical under dual numbering |
Identical/Equivalent Standards : | IEC TS 61496-5 : 2023 |
Organization Type: | IEC |
Sl.No. | Synosis Points | |
1 | This part of IEC 61496 provides particular requirements for the design, construction and testing of non-contact electro-sensitive protective equipment (ESPE) designed specifically to provide whole-body detection of a person or persons as part of a safety-related system, employing radar protective devices (RPDs) responsive to diffuse reflection of radar signals for the sensing function using frequency-modulated continuous-wave (FMCW) technique. Special attention is directed to features which ensure that an appropriate safety-related performance is achieved. An ESPE can include optional safety-related functions, the requirements for which are given in Annex A of IEC 61496-1:2020 and Annex A of this document. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 15-04-2021 | ------- | ||
2 | P-Draft | 25-06-2024 | Covering letter generated | ------- | |
3 | P-Draft | 25-06-2024 | Duration : 30 Days | ETD 44, | ------- |
4 | Skipped to W-Draft | 21-02-2025 | Stage-Changed | ------- | |
5 | WC Draft | 21-02-2025 | Duration : 60 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 22-02-2025 | WC approved by HOD |
ETDC ETD 44, | ------- |