Document Details
Name of Department/Committee : ETD 44
Document Number : ETD 44 ( 25966)
Document Title [English] : Safety of Machinery Electro-Sensitive Protective Equipment Part 5 Particular Requirements for Radar-Based Protective Devices
Document Title [Hindi] : मशीनों की सुरक्षा - विद्युत संवेदी संरक्षी उपकरण - भाग 5 रडार आधारित संरक्षी उपकरणों के लिए विशेष अपेक्षाएं
Document Type : New
Language : English
Priority : 2
ICS Code : ICS 13.110; 29.260.99
Date of Project Approval : 15-04-2021
Standards to be Superseded :


Classification Details
Group : Electrical Switchgear and Other Electrical Products/Accessories
Sub Group : Electrical installations and general electricals
Sub Sub Group : National Electrical Code
Aspects : Safety Standard
Risk : Low
Certification : None
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Heavy Industries
Sustainable development Goals :
Degree of Equivalence : Identical under dual numbering
Identical/Equivalent Standards : IEC TS 61496-5 : 2023
Organization Type: IEC

Sl.No. Synosis Points
1 This part of IEC 61496 provides particular requirements for the design, construction and testing of non-contact electro-sensitive protective equipment (ESPE) designed specifically to provide whole-body detection of a person or persons as part of a safety-related system, employing radar protective devices (RPDs) responsive to diffuse reflection of radar signals for the sensing function using frequency-modulated continuous-wave (FMCW) technique. Special attention is directed to features which ensure that an appropriate safety-related performance is achieved. An ESPE can include optional safety-related functions, the requirements for which are given in Annex A of IEC 61496-1:2020 and Annex A of this document.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 24-06-2024 24-10-2024 24-11-2024 24-03-2025 Ms. ANKITA TRIPATHI 24-06-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 15-04-2021 -------
2 P-Draft 25-06-2024 Covering letter generated -------
3 P-Draft 25-06-2024 Duration : 30 Days ETD 44, -------
4 Skipped to W-Draft 21-02-2025 Stage-Changed -------
5 WC Draft 21-02-2025 Duration : 60 Days
Submitted for HOD approval
-------
6 WC Draft 22-02-2025 WC approved by HOD
ETDC  ETD 44, -------