Document Details
Name of Department/Committee : WRD 24
Document Number : WRD 24 ( 25811)
Document Title [English] : Preparation of Catchment Area Treatment (CAT) Plan — Guidelines
Document Title [Hindi] : जलग्रहण क्षेत्र उपचार योजना की तैयारी — दिशानिर्देश
Document Type : New
Language : English
Priority : 3
ICS Code : 13.020.30
Date of Project Approval : 16-04-2024
Standards to be Superseded :


Classification Details
Group : Environment Services
Sub Group : Environment Services
Sub Sub Group : Environment-related services
Aspects : Code of Practice
Risk : Low
Certification : None
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Environment, Forest and Climate Change
  • Ministry of Jal Shakti - Department of Water Resources, River Development and Ganga Rejuvenation
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 Man-nature conflict, to meet the un-satiating demands of land and other natural resources like fuel wood, fodder, etc., has resulted in overexploitation of the limited natural resources. Encroachment of forests and pasture lands and faulty agricultural practices have further aggravated the problem of land degradation and soil erosion. Heavy soil erosion from the degraded patches of the catchment, results in sedimentation of the reservoir, thereby reducing its storage capacity and impeding the life span of a river valley project.
2 In order to address the menace of soil erosion, proper soil and water conservation measures are required to be implemented as a part of the catchment area treatment (CAT) strategy. An ideal CAT intervention should focus on checking the soil erosion at the source, addressing the landslide hazards in the direct impact zone of a project, checking the sediment load from the tributaries directly discharging into the reservoir, and protecting the directly draining catchment from scouring/sloughing and slips.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 16-04-2024 31-12-2024 31-03-2025 30-09-2025 Mr. Vaibhav Jindal 05-06-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 16-04-2024 -------
2 P-Draft Waived 05-06-2024 -------
3 WC Draft 11-06-2024 Duration : 60 Days
Submitted for HOD approval
-------
4 WC Draft 13-06-2024 WC approved by HOD
WRDC  WRD 24, -------