Name of Department/Committee : PGD 04
Document Number : PGD 04 ( 25778)
Document Title [English] : Tools for Pressing Gas Springs Part 5: Safety Instructions for Gas Springs
Document Title [Hindi] : दबाने के लिए उपकरण - गैस स्प्रिंग्स – भाग 5: गैस स्प्रिंग्स के लिए सुरक्षा अनुदेश
Document Type : New
Language : English
Priority : 3
ICS Code : ICS 25.120.10
Date of Project Approval : 31-05-2024
Standards to be Superseded :


Classification Details
Group : Gases, Gas Cylinders , Machine tools and other mechanical products
Sub Group : Hand tools and machine components
Sub Sub Group : Machines Presses & Press Work
Aspects : Product Specification
Risk : None
Certification : Mandatory Certification
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Commerce and Industry - Department for Promotion of Industry and Internal Trade (DPIIT)
Sustainable development Goals :
Degree of Equivalence : Identical under dual numbering
Identical/Equivalent Standards : ISO 11901-5 : 2021
Organization Type: ISO

Sl.No. Synosis Points
1 This Standard describes the safety requirements for gas springs in accordance with ISO 11901-1, ISO 11901-3 and ISO 11901-4 intended for use in press tool and their correct installation instructions.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 31-05-2024 31-10-2024 15-01-2025 30-05-2025 Mr. VIMAL KUMAR 31-05-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 31-05-2024 -------
2 P-Draft Waived 06-06-2024 -------
3 WC Draft 06-06-2024 Duration : 30 Days
Submitted for HOD approval
-------
4 WC Draft 06-06-2024 WC rejected by HOD
Remarks: Please write Doc.: PGD 04 (25775) WC
-------
5 WC Draft 07-06-2024 Duration : 30 Days
Submitted for HOD approval
Remarks : Corrections made as discussed please approve the WC-Draft
-------
6 WC Draft 10-06-2024 WC rejected by HOD
Remarks: Please correct as discussed.
-------
7 WC Draft 01-07-2024 Duration : 30 Days
Submitted for HOD approval
-------
8 WC Draft 01-07-2024 WC approved by HOD
PGDC   -------