Document Details |
|
Name of Department/Committee : | ETD 25 |
---|---|
Document Number : | ETD 25 ( 24387) |
Document Title [English] : | IS 17900: LIFTS FOR THE TRANSPORT OF PERSONS AND GOODS: PART 7: LIFTS FOR SPECIAL APPLICATIONS: SECTION 2: RACK AND PINION LIFTS USED IN UNDER-CONSTRUCTION BUILDINGS |
Document Title [Hindi] : | IS 17900: व्यक्तियों और वस्तुओं के परिवहन के लिए लिफ्ट भाग 7: विशेष अनुप्रयोगों के लिए लिफ्टें अनुभाग 2: निर्माणाधीन इमारतों में प्रयुक्त रैक और पिनियन लिफ्ट |
Document Type : | New |
Language : | English |
Priority : | 3 |
ICS Code : | 91.140.90 |
Date of Project Approval : | 23-11-2023 |
Standards to be Superseded : |
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Electrical installations and general electricals |
Sub Sub Group : | Elevators & Escalators |
Aspects : | Product Specification |
Risk : | None |
Certification : | None |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | This standard specifies requirements for the Rack and Pinion type of Temporary Lifts that are used during construction stage in under-construction buildings to transport instructed people who are authorized to enter the site, tools and materials used for construction of the building. In case of Rack and Pinion type of Temporary Lifts used in Under-Construction-Buildings, full compliance with IS 17900-1and IS 17900-2 is required. | |
2 | This standard is not applicable to the Rack & Pinion Lifts permanently installed in any location. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 23-11-2023 | ------- | ||
2 | P-Draft Waived | 08-12-2023 | ------- | ||
3 | WC Draft | 08-12-2023 | Duration : 60 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 11-12-2023 | WC approved by HOD |
ETDC ETD 25, | ------- |