Document Details
Name of Department/Committee : PGD 37
Document Number : PGD 37 ( 24265)
Document Title [English] : Technical Supply Condition for Threaded Steel Fasteners Part 12 Phosphate Coatings on Threaded Fasteners Second Revision
Document Title [Hindi] : इस्पात के चूड़ीदार बंधको की तकनीकी पूर्ति शर्तें भाग 12 थ्रेडेड फास्टनरों पर फॉस्फेट कोटिंग
Document Type : Revision
Language : English
Priority : 3
ICS Code : 21.060.20
Date of Project Approval : 12-10-2023
Standards to be Revised :
Sl.No. Is No & Year
1 IS 1367 : Part 12: 1981
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 1367 : Part 12: 1981


Classification Details
Group : Building Materials including Paints
Sub Group : Fasteners and hardware
Sub Sub Group : Fastners
Aspects : Others
Risk : None
Certification : Not Certifiable
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Commerce and Industry - Department for Promotion of Industry and Internal Trade (DPIIT)
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 This standard covers the requirements of threaded steel fasteners with phosphate coating of either zinc phosphate (ZnPh) or manganese phosphate (MnPh), that is intended to be used in conjunction with a sealant for protection against corrosion.
2 In this revision following changes have been made: a) Scope of the standard has been revised to cover the requirements of manganese phosphate coating on fasteners; b) Neutral salt spray (NSS) for testing corrosion resistance of fasteners has been revised based on the latest international practices; and c) References have been updated.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 28-11-2023 28-04-2024 13-07-2024 28-11-2024 Mr. MONARCH JOSHI 28-11-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 12-10-2023 -------
2 P-Draft 28-11-2023 Covering letter generated -------
3 P-Draft 28-11-2023 Duration : 30 Days PGD 37, -------
4 Skipped to W-Draft 20-01-2025 Stage-Changed -------
5 WC Draft 31-01-2025 Duration : 30 Days
Submitted for HOD approval
Remarks : Corrections have been made as marked in the hard copy Submitted for your kind approval please
-------
6 WC Draft 31-01-2025 WC rejected by HOD
Remarks: Please correct the reference clause
-------