Date of Project Approval : 20-11-2023
Standards to be Revised :
Sl.No. Is No & Year
1 IS 14492: 1997
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 14492: 1997


Classification Details
Group : Metals, Alloys and Metal Products (including Steel Products)
Sub Group : Furnace and its accessories
Sub Sub Group : Code of Practice, Glossary on Furnaces
Aspects : Code of Practice
Risk : None
Certification : None
Short Commom Man's Title : Drying, pre-heating and commissioning of furnace installations, steam boilers, industrial kilns and
ITCHS Code :
Ministry :
  • Ministry of Steel
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 This standard outlines the recommendations for the drying pre-heating and commissioning of furnace installations, steam boilers, industrial kilns and chimneys. 1.1 This standard does not cover chemical furnaces.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 20-11-2023 20-04-2024 05-07-2024 20-11-2024 SHIV PRAKASH 20-11-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 20-11-2023 -------
2 P-Draft 24-11-2023 Covering letter generated -------
3 P-Draft 24-11-2023 Duration : 21 Days MTD 26, -------
4 Skipped to W-Draft 06-05-2024 Stage-Changed -------
5 WC Draft 06-05-2024 Duration : 30 Days
Submitted for HOD approval
Remarks : For your comments and inputs please
-------
6 WC Draft 06-05-2024 Duration : 30 Days
Submitted for HOD approval
Remarks : For your kind comments and inputs please
-------
7 WC Draft 21-05-2024 WC rejected by HOD
Remarks: Please update the dates
-------
8 WC Draft 29-05-2024 Duration : 30 Days
Submitted for HOD approval
-------
9 WC Draft 31-05-2024 WC rejected by HOD
Remarks: please modify as discussed
-------
10 WC Draft 31-05-2024 Duration : 30 Days
Submitted for HOD approval
-------
11 WC Draft 31-05-2024 WC approved by HOD
MTDC   -------