Document Details |
|||||
Name of Department/Committee : | LITD 10 | ||||
---|---|---|---|---|---|
Document Number : | LITD 10 ( 24782) | ||||
Document Title [English] : | Power Control Systems Security Requirements First Revision | ||||
Document Title [Hindi] : | पावर कंट्रोल सिस्टम - सुरक्षा आवश्यकताएँ (पहला पुनरीक्षण) | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | ICS 33.200 | ||||
Date of Project Approval : | 30-01-2024 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Electronic and Telecom equipments, components and devices |
Sub Group : | Power system control and communication |
Sub Sub Group : | Power System Control and Communications |
Aspects : | Others |
Risk : | None |
Certification : | None |
Short Commom Man's Title : | Power Control Systems - Security Requirements |
ITCHS Code : | NA |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | The objective of this standard is to provide guidelines for the protection of critical assets for all entities involved in generation, transmission, distribution, grid operation and trading of electric power. Safety, security, and reliability have always been important issues in the design and operation of systems in the power industry. In recent years, information security has also come into prominence owing to the presence of multiple competing entities that need to exchange relevant information but at the same time protect confidential critical information infrastructure. | |
2 | In preparing this standard, considerable text has been derived from NERC CIP, IEC 62443 and IEC 62351 standards. The Working Group members acknowledge and appreciate the efforts of the NERC Committee which draft the Critical Infrastructure Protection Standards. | |
3 | The aspect of cyber security is fast changing and over a period of time the necessary standards and guidelines viz., IEC 62351 series, ISO/IEC 27000 series, IEC 62443 series, NERC CIP were revised/amended/new part(s) included and guidelines/order/regulation on the object were issued across the globe including India for providing best protection and for ascertaining grid resiliency. To incorporate these changes, IS 16353 has been revised. In the revised standard, some of the text have been modified to reflect the changes in the aforementioned standards/guidelines. A few new term & definitions have been added. Also a new clause on the requirements of supply chain risk management has been specified. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 30-01-2024 | ------- | ||
2 | P-Draft | 06-02-2024 | Covering letter generated | ------- | |
3 | P-Draft | 06-02-2024 | Duration : 30 Days Remarks : The committee decided to issue preliminary draft for a period of 30 days All committee members are requested to provide their inputs and comments on or before 2nd of March 2024 |
LITD 10, LITD 10 : P2, LITD 10 : P3, LITD 10 : P4, LITD 10 : P5, LITD 10 : P6, LITD 10 : P8, | ------- |
4 | Skipped to W-Draft | 05-04-2024 | Stage-Changed | ------- | |
5 | WC Draft | 05-04-2024 | Duration : 60 Days Submitted for HOD approval Remarks : Wide Circulation |
------- | |
6 | WC Draft | 19-04-2024 | WC approved by HOD |
LITDC | ------- |
7 | WC Draft | 19-11-2024 | Duration : 60 Days Submitted for HOD approval Remarks : Wide Circulation |
------- | |
8 | WC Draft | 20-11-2024 | WC approved by HOD |