Document Details
Name of Department/Committee : LITD 10
Document Number : LITD 10 ( 24782)
Document Title [English] : Power Control Systems Security Requirements First Revision
Document Title [Hindi] : पावर कंट्रोल सिस्टम - सुरक्षा आवश्यकताएँ (पहला पुनरीक्षण)
Document Type : Revision
Language : English
Priority : 3
ICS Code : ICS 33.200
Date of Project Approval : 30-01-2024
Standards to be Revised :
Sl.No. Is No & Year
1 IS 16335 : 2015
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 16335 : 2015


Classification Details
Group : Electronic and Telecom equipments, components and devices
Sub Group : Power system control and communication
Sub Sub Group : Power System Control and Communications
Aspects : Others
Risk : None
Certification : None
Short Commom Man's Title : Power Control Systems - Security Requirements
ITCHS Code : NA
Ministry :
  • Ministry of Electronics and Information Technology
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 The objective of this standard is to provide guidelines for the protection of critical assets for all entities involved in generation, transmission, distribution, grid operation and trading of electric power. Safety, security, and reliability have always been important issues in the design and operation of systems in the power industry. In recent years, information security has also come into prominence owing to the presence of multiple competing entities that need to exchange relevant information but at the same time protect confidential critical information infrastructure.
2 In preparing this standard, considerable text has been derived from NERC CIP, IEC 62443 and IEC 62351 standards. The Working Group members acknowledge and appreciate the efforts of the NERC Committee which draft the Critical Infrastructure Protection Standards.
3 The aspect of cyber security is fast changing and over a period of time the necessary standards and guidelines viz., IEC 62351 series, ISO/IEC 27000 series, IEC 62443 series, NERC CIP were revised/amended/new part(s) included and guidelines/order/regulation on the object were issued across the globe including India for providing best protection and for ascertaining grid resiliency. To incorporate these changes, IS 16353 has been revised. In the revised standard, some of the text have been modified to reflect the changes in the aforementioned standards/guidelines. A few new term & definitions have been added. Also a new clause on the requirements of supply chain risk management has been specified.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 06-02-2024 06-07-2024 21-09-2024 05-02-2025 MS. ALISMITA KHAG 06-02-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 30-01-2024 -------
2 P-Draft 06-02-2024 Covering letter generated -------
3 P-Draft 06-02-2024 Duration : 30 Days
Remarks : The committee decided to issue preliminary draft for a period of 30 days All committee members are requested to provide their inputs and comments on or before 2nd of March 2024
LITD 10, LITD 10 : P2, LITD 10 : P3, LITD 10 : P4, LITD 10 : P5, LITD 10 : P6, LITD 10 : P8,  -------
4 Skipped to W-Draft 05-04-2024 Stage-Changed -------
5 WC Draft 05-04-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : Wide Circulation
-------
6 WC Draft 19-04-2024 WC approved by HOD
LITDC   -------
7 WC Draft 19-11-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : Wide Circulation
-------
8 WC Draft 20-11-2024 WC approved by HOD
LITDC   -------