Document Details
Name of Department/Committee : SSD 14
Document Number : SSD 14 ( 24778)
Document Title [English] : Alternative Drinking Water Service Provision During a Crisis Guidelines
Document Title [Hindi] : संकट के दौरान वैकल्पिक पेयजल सेवा प्रावधान - दिशानिर्देश
Document Type : New
Language : English
Priority : 3
ICS Code : 03.080.30; 13.060.20
Date of Project Approval : 12-01-2024
Standards to be Superseded :


Classification Details
Group : Environment Services
Sub Group : Environment Services
Sub Sub Group : Environment-related services
Aspects : Service Specification
Risk : Low
Certification : Not Certifiable
Short Commom Man's Title : ADWS
ITCHS Code :
Ministry :
  • Ministry of Jal Shakti
  • Ministry of Housing and Urban Affairs
  • Ministry of Environment, Forest and Climate Change
Sustainable development Goals :
  • GOOD HEALTH AND WELL BEING
  • CLEAN WATER AND SANITATION
  • REDUCED INEQUALITY
  • SUSTAINABLE CITIES AND COMMUNITIES
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 This standard is intended for drinking water utilities that normally provide a service without interruption through a drinking water supply system. It provides guidelines for the effective implementation of alternative drinking water service (ADWS) provision during extended periods of disruption to the drinking water supply

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 05-02-2024 05-07-2024 20-09-2024 04-02-2025 Ms. PRIYANKA SINGH 05-02-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 12-01-2024 -------
2 P-Draft 05-02-2024 Covering letter generated -------
3 P-Draft 05-02-2024 Duration : 28 Days SSD 14, -------
4 Skipped to W-Draft 23-04-2024 Stage-Changed -------
5 WC Draft 23-04-2024 Duration : 60 Days
Submitted for HOD approval
-------
6 WC Draft 01-05-2024 WC rejected by HOD
Remarks: Please review the document as discussed
-------
7 WC Draft 02-05-2024 Duration : 60 Days
Submitted for HOD approval
-------
8 WC Draft 02-05-2024 WC rejected by HOD
Remarks: Please review the period of WC mentioned in the document
-------
9 WC Draft 03-05-2024 Duration : 60 Days
Submitted for HOD approval
-------
10 WC Draft 07-05-2024 WC rejected by HOD
Remarks: Review foreword and font size of the document
-------
11 WC Draft 07-05-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : modified draft document is recommended for approval
-------
12 WC Draft 07-05-2024 WC rejected by HOD
Remarks: Review clause no under Annex C and D. Also Fig E in contents and mentioned below Fig are not matching. Please review the entire document.
-------
13 WC Draft 09-05-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : modified draft document is recommended for approval
-------
14 WC Draft 10-05-2024 WC approved by HOD
SSDC  CED 24, FAD 14, CHD 32, CHD 36, -------