Document Details |
|
Name of Department/Committee : | ETD 20 |
---|---|
Document Number : | ETD 20 ( 24499) |
Document Title [English] : | Lightning protection system components LPSC Part 2: Requirements for conductors and earth electrodes |
Document Title [Hindi] : | विद्युत संरक्षण प्रणाली कम्पोनेंट्स (एलपीएससी) - भाग 2: चालकों और अर्थ इलेक्ट्रोड के लिए आवश्यकताएँ |
Document Type : | New |
Language : | English |
Priority : | 3 |
ICS Code : | 29.020; 91.120.40 |
Date of Project Approval : | 27-12-2023 |
Standards to be Superseded : |
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Electrical installations and general electricals |
Sub Sub Group : | National Electrical Code |
Aspects : | Product Specification |
Risk : | Medium |
Certification : | Voluntary Certification |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Identical under dual numbering |
Identical/Equivalent Standards : | IEC 62561-2-2018 |
Organization Type: | IEC |
::Cross Referenced Indian Standard:: |
|||
Sl. No. | Is No & Year | IS Title | |
1 | IS/IEC 62305 : Part 4: 2010 | Protection against lightning: Part 4 electrical and electronic systems within stuctures | |
2 | IS/IEC 62305 : Part 4: 2010 | Protection against lightning: Part 4 electrical and electronic systems within stuctures |
Sl.No. | Synosis Points | |
1 | This standard specifies the requirements and tests for: - metallic conductors (other than "natural" conductors) that form part of the air-termination and down-conductor systems, - metallic earth electrodes that form part of the earth-termination system. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 27-12-2023 | ------- | ||
2 | P-Draft Waived | 27-12-2023 | ------- | ||
3 | WC Draft | 27-12-2023 | Duration : 60 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 27-12-2023 | WC approved by HOD |
ETDC ETD 20, | ------- |
5 | Skipped to Finalization | 21-07-2024 | Stage-Changed | ------- | |
6 | Finalization | 18-06-2024 | Electrical Installations Sectional Committee ETD 20 during its 41st meeting held on 18th June 2024 approved the document for printing | ------- | |
7 | Final Draft | 21-07-2024 | Submited for HOD approval Remarks: Electrical Installations Sectional Committee ETD 20 during its 41st meeting held on 18th June 2024 approved the document for printing |
------- | |
8 | Final Draft draft accepted by HOD and sent to Publication | 22-07-2024 | Final Draft approved by HOD | ------- |