Name of Department/Committee : MTD 13
Document Number : MTD 13 ( 23674)
Document Title [English] : DETERMINATION OF COMPRESSION STRENGTH OF IRON ORE PELLETS AFTER REDUCTION - METHOD First Revision
Document Title [Hindi] : छंटनी के बाद लौह अयस्क छर्रों की संपीड़न शक्ति का निर्धारण – पद्धति
Document Type : Revision
Language : English
Priority : 3
ICS Code : 77.100
Date of Project Approval : 11-08-2023
Standards to be Revised :
Sl.No. Is No & Year
1 IS 8604: 1977
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 8604: 1977


Classification Details
Group : Metals, Alloys and Metal Products (including Steel Products)
Sub Group : Ores and sponge iron, ferro alloys and other metallic additions
Sub Sub Group : Test Methods of ores
Aspects : Methods of tests
Risk : None
Certification : None
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Steel
Sustainable development Goals :
Degree of Equivalence : Not Equivalent
Identical/Equivalent Standards : ISO 4700:2015
Organization Type: ISO

Sl.No. Synosis Points
1 The standard was first published in 1977. This revision has been brought out to bring the standard in the latest style and format of the Indian Standards. In addition, the following changes have been made: a) Scope clause has been modified; b) References clause has been included; c) In clause 3, editorial change has been made, d) In clause 4, apparatus clause has been modified; e) In clause 4.2, speed of the compressive platen is modified from ‘5 mm/min’ to ‘between 10 mm/min and 20 mm/min’; f) In clause 4.3, applied load is modified from ‘200 kg’ to ‘atleast 10 kN’; g) In clause 5, sampling clause has been modified; h) Procedure clause has been modified; i) 2 figures to measure crushing strength were indicated; and j) Test report clause has been modified.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 26-09-2023 26-02-2024 11-05-2024 26-09-2024 Mr. RAM SAI KUMAR GEDELA 26-09-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 11-08-2023 -------
2 P-Draft Waived 03-10-2023 -------
3 WC Draft 03-10-2023 Duration : 31 Days
Submitted for HOD approval
-------
4 WC Draft 04-10-2023 WC approved by HOD
MTDC  MTD 13, -------