Document Details |
|||||
Name of Department/Committee : | WRD 06 | ||||
---|---|---|---|---|---|
Document Number : | WRD 06 ( 22547) | ||||
Document Title [English] : | PROFORMA FOR REPORTING PROGRESS DURING CONSTRUCTION FOR RIVER VALLEY PROJECTS PART 3 FLOOD CONTROL First Revision of IS 13218 Part 3 | ||||
Document Title [Hindi] : | नदी घाटी परियोजना के निर्माण के दौरान हुई प्रगति की रिपोर्ट देने के लिए प्रपत्र भाग 3 बाढ़ नियंत्रण (IS 13218 भाग 3 का पहला पुनरीक्षण) | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | 93.160 | ||||
Date of Project Approval : | 29-05-2023 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Civil Engineering Design and Construction |
Sub Group : | Hydraulic and other related structures |
Sub Sub Group : | Water Resources Planning Mangement and Evaluation of river valley and irrigation projects |
Aspects : | Others |
Risk : | None |
Certification : | Not Certifiable |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : |
|
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | The object of monitoring is to identify bottlenecks and to ensure expeditious completion of schemes. Monitoring shall cover various stages of the project right from the conception stage to data collection, investigations planning, sanction, implementation, and operation. The performance would ensure the identification of bottlenecks and monitoring of progress, relating to any preset programme. This revision has been brought out in view of the various technological changes that have taken place in this field since 1992 and also to incorporate the latest practices prevalent in this field. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 29-05-2023 | ------- | ||
2 | P-Draft | 29-05-2023 | Covering letter generated | ------- | |
3 | P-Draft | 29-05-2023 | Duration : 15 Days | WRD 6, | ------- |
4 | Skipped to W-Draft | 20-10-2023 | Stage-Changed | ------- | |
5 | WC Draft | 20-10-2023 | Duration : 60 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 31-10-2023 | WC approved by HOD |
WRDC | ------- |
7 | WC-Draft | 07-11-2023 | WC-Draft Email Notifications Sent | WRDC, WRD 6, | ------- |