Name of Department/Committee : TED 22
Document Number : TED 22 ( 20795)
Document Title [English] : POWERED INDUSTRIAL TRUCKS - TERMINOLOGY (Fourth Revision)
Document Title [Hindi] : पावरचालित औद्योगिक ट्रकों की पारिभाषिक शब्दावली - (चौथा पुनरीक्षण)
Document Type : Revision
Language : English
Priority : 3
ICS Code : 53.060
Date of Project Approval : 22-02-2022
Standards to be Revised :
Sl.No. Is No & Year
1 IS 4660: 1993
2 IS 4660: 1993
3 IS 4660: 1993
Standards to be Superseded :


Classification Details
Group : Transport and Related Products
Sub Group : Automobiles and their components
Sub Sub Group : Industrial trucks, their attachments & Components
Aspects : Terminology
Risk : Low
Certification : None
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Road Transport and Highways
Sustainable development Goals :
Degree of Equivalence : Modified/Technically Equivalent
Identical/Equivalent Standards : ISO 5053: 1987
Organization Type: ISO

Sl.No. Synosis Points
1 This standard specifies the various terms used for powered industrial trucks, its components and accessories. Some terms are not being defined, because they are self-evident or because they are in general use elsewhere such as petrol trucks/diesel trucks. This standard also defines the terms relating to industrial trailer and operating areas where such trucks are expected to be used (see Annex A).

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 17-10-2022 17-03-2023 01-06-2023 16-10-2023 Mr. AUGUST DUBEY 17-10-2022
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 22-02-2022 -------
2 P-Draft 17-10-2022 Covering letter generated -------
3 P-Draft 17-10-2022 Duration : 30 Days TED 22, -------
4 Skipped to W-Draft 26-07-2023 Stage-Changed -------
5 WC Draft 09-05-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : In 27th Meeting of TED 22 committee decided to process the draft for WC for 60 days
-------
6 WC Draft 09-05-2024 WC approved by HOD
TEDC  TED 22, -------
7 WC Draft 16-08-2024 Stage-Changed -------
8 WC Draft 20-08-2024 As per request received from TED Department through email dated 19/08/2024, the document stage has been rolled back -------
9 WC Draft 30-08-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : Few Additions were made by Committee Members
-------
10 WC Draft 04-09-2024 WC approved by HOD
TEDC  TED 22, -------