Document Details
Name of Department/Committee : MED 08
Document Number : MED 08 ( 20461)
Document Title [English] : STEEL HEADFRAMES FOR MINES PART 1 PRINCIPLES OF LOAD COMPUTATION AND APPLICABLE FACTORS OF SAFETY
Document Title [Hindi] : खदान के लिए स्टील हेडफ्रेम भाग 1 लोड गणना के लिए सिद्धांत और सुरक्षा के लिए लागू कारक
Document Type : Revision
Language : English
Priority : 3
ICS Code : 73.100.01
Date of Project Approval : 05-09-2022
Standards to be Revised :
Sl.No. Is No & Year
1 IS 12450 : Part 1: 1988
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 12450 : Part 1: 1988


Classification Details
Group : Gases, Gas Cylinders , Machine tools and other mechanical products
Sub Group : Conveyors, hoisting and lifting equipments and rope ways
Sub Sub Group : Mine cage suspensions
Aspects : Code of Practice
Risk : Low
Certification : Not Certifiable
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Commerce and Industry - Department for Promotion of Industry and Internal Trade (DPIIT)
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 The standard lays down the principles of load computation and applicable factors of safety for steel headframes for mines used under normal and special operating conditions. This standard is not applicable to winding towers where a winding engine is installed on top of the headframe structure.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 05-09-2022 05-02-2023 20-04-2023 04-09-2023 SHRI SANDEEP KESHAV 05-09-2022
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 05-09-2022 -------
2 P-Draft Waived 05-09-2022 The committee MED 08 in its 23rd meeting decided to wide-circulate the draft waiving its P-draft stage. -------
3 WC Draft 05-09-2022 Duration : 60 Days
Submitted for HOD approval
Remarks : The document is being wide-circulated for 2 months time for public commenting
-------
4 WC Draft 07-09-2022 WC rejected by HOD
Remarks: Please Check.
-------
5 WC Draft 08-09-2022 Duration : 60 Days
Submitted for HOD approval
Remarks : Document corrected The document is being wide-circulated for 60 days for public commenting
-------
6 WC Draft 12-09-2022 WC approved by HOD
MEDC   -------