Document Details
Name of Department/Committee : PGD 34
Document Number : PGD 34 ( 18691)
Document Title [English] : TRACK SPANNERS FOR RAILWAYS SPECIFICATIONS
Document Title [Hindi] : रेलवे के लिए ट्रैक पाना — विशिष्टि
Document Type : Revision
Language : English
Priority : 3
ICS Code : 25.140.30
Date of Project Approval : 29-06-2021
Standards to be Revised :
Sl.No. Is No & Year
1 IS 4485: 1968
Standards to be Superseded :
Sl.No. Is No & Year
1 IS 4485: 1968


Classification Details
Group : Gases, Gas Cylinders , Machine tools and other mechanical products
Sub Group : Hand tools and machine components
Sub Sub Group : General Hand Tools
Aspects : Product Specification
Risk : Low
Certification : Voluntary Certification
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Micro, Small and Medium Enterprises
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 This draft standard specifies the requirements for track spanners used by the railways.
2 In this revision, the following changes have been made: a) Clause on references has been added; b) Material designations have been updated as per the latest Indian Standard.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 30-04-2022 14-01-2023 29-05-2023 29-12-2023 Mr. VIMAL KUMAR 30-12-2021
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 29-06-2021 -------
2 P-Draft Waived 30-12-2021 -------
3 WC Draft 30-12-2021 Duration : 90 Days
Submitted for HOD approval
-------
4 WC Draft 05-01-2022 WC rejected by HOD
Remarks: Kindly modify as discussed
-------
5 WC Draft 18-01-2022 Duration : 90 Days
Submitted for HOD approval
Remarks : The draft has been modified kindly approve for WC
-------
6 WC Draft 28-01-2022 WC rejected by HOD
Remarks: Kindly change APPENDIX with ANNEX in page no. 6
-------
7 WC Draft 11-05-2022 Duration : 90 Days
Submitted for HOD approval
-------
8 WC Draft 12-05-2022 WC approved by HOD
PGDC   -------